For HE-I
01. Opening
& dismantling of cooling water inlet& outlet flanges from 4 inch
cooling water manifold line from tube bundle to enable for lifting 4 nos. (One
manifold in each tube bundle & two flanges in one manifold)
02. Dismantling
of inlet & outlet 6 inch cooling water line of each interstage coolers
03. Opening
& dismantling of cooling water tube bundle top head from each tube sheet
04. Opening,
lifting & then lowering of four water tube bundles.
Each tube bundle weighs 2 MT approx. and laying it properly.
05. Opening
& dismantling of cooling water tube bundle bottom head from each tube
sheet.
06. Opening,
lifting & then lowering of the separator (weighs 0.5 MT approx.) and laying
it properly.
07. Dismantling
of all cooler drain & drain by-pass system flanges for choke clearing.
08. Proper
cleaning of all flange-jointing areas.
09. Cutting
of all necessary gaskets in proper dimensions from supplied gasket sheets.
10. Fitting
of gaskets properly without damage in all appropriate positions.
11. Fitting,
assembling & boxing up the manifolds, pipe lines, tube bundles, etc.
12. Appropriate
tightening of all nuts-bolts.
13. Making
& fitting of all appropriate jacking/ lifting arrangement by cutting,
welding, grinding works.
14. All the
tools & tackles, cutting & welding appliances and accessories shall be
adequately supplied by the executing agency.
15. All best
engineering practices & procedures and safety gadgets to be strictly
followed while working.
16. Assembling/Dismantling
of scaffoldings.
17. Carrying/cleaning
of site debris/waste to dumping yard after finishing of job.
18. Returning
of unused supplied material(s) to the Engineer-in-charge.
19. Job
shall be executed as instructed by Engineer-in-charge.
For HE-3
- Opening
& dismantling of cooling water inlet& outlet flanges from 4 inch
cooling water manifold line from tube bundle to enable for lifting 3 nos. (One
manifold in each tube bundle & two flanges in one manifold)
- Dismantling
of inlet & outlet 6 inch cooling water line of each interstage coolers
- Opening
& dismantling of cooling water tube bundle top head from each tube
sheet
- Opening,
lifting & then lowering of three water tube
bundles. Each tube bundle weighs 2 MT approx. and laying it
properly.
- Opening
& dismantling of cooling water tube bundle bottom head from each tube
sheet.
- Opening,
lifting & then lowering of the separator (weighs 0.5 MT approx.) and
laying it properly.
- Dismantling
of all cooler drain & drain by-pass system flanges for choke clearing.
- Proper
cleaning of all flange-jointing areas.
- Cutting
of all necessary gaskets in proper dimensions from supplied gasket sheets.
- Fitting
of gaskets properly without damage in all appropriate positions.
- Fitting,
assembling & boxing up the manifolds, pipe lines, tube bundles, etc.
- Appropriate
tightening of all nuts-bolts.
- Making
& fitting of all appropriate jacking/ lifting arrangement by cutting,
welding, grinding works.
- All
the tools & tackles, cutting & welding appliances and accessories
shall be adequately supplied by the executing agency.
- All
best engineering practices & procedures and safety gadgets to be
strictly followed while working.
- Assembling/Dismantling
of scaffoldings.
- Carrying/cleaning
of site debris/waste to dumping yard after finishing of job.
- Returning
of unused supplied material(s) to the Engineer-in-charge.
- Job
shall be executed as instructed by Engineer-in-charge.